Skip to main content
Capital Planning
Brandon Smith3 min read
Technician monitoring risk assessment displays and equipment health data in a food manufacturing facility

A beverage facility plans a 4-month equipment upgrade. The project schedule includes: equipment delivery (6 weeks), installation (4 weeks), commissioning (4 weeks).

What the schedule doesn't account for:

  • Equipment supplier delays (historical 2-3 weeks common in food equipment)
  • Electrical infrastructure upgrades (discovered during installation, adding 3-4 weeks)
  • Integration challenges with existing SCADA (adding 2 weeks to controls work)
  • Regulatory approval delays (6-8 weeks for facility modification permits)

The planned 4-month project becomes 7-8 months. The facility loses revenue for 3-4 extra months.

This is a risk management failure—risks existed but weren't identified or mitigated.

The Risk Identification Process

During FEL (feasibility studies), identify risks by category:

Schedule Risks:

  • Long-lead equipment (over 8 weeks delivery): HIGH
  • Utility infrastructure upgrades: HIGH
  • Regulatory approvals: MEDIUM
  • Facility modifications (construction): MEDIUM
  • Controls integration: MEDIUM

Cost Risks:

  • Site condition discoveries: HIGH
  • Equipment price escalation: MEDIUM
  • Labor cost inflation: MEDIUM
  • Vendor change order requests: MEDIUM

Technical Risks:

  • New technology with limited food manufacturing experience: HIGH
  • Equipment integration with old systems: MEDIUM
  • Process parameter uncertainty: MEDIUM

Regulatory Risks:

  • FDA or USDA approval required: HIGH
  • Environmental discharge permit: MEDIUM
  • Local building permits: MEDIUM

Risk Mitigation Strategies

For each identified risk, develop mitigation:

Schedule Risk (Equipment Lead Time):

  • Mitigation: Order equipment 8 weeks before needed installation date
  • Fallback: Identify backup supplier willing to expedite
  • Cost: Minimal (planning)

Schedule Risk (Electrical Upgrade):

  • Mitigation: Commission electrical assessment during FEL ($5K-10K)
  • Plan upgrade timeline before project execution
  • Cost: $5K-10K investigation + identified upgrade cost

Technical Risk (Controls Integration):

  • Mitigation: Engage controls integrator early in FEL
  • Run integration tests during commissioning phase
  • Cost: Early engineering ($10K) + commissioning time

Regulatory Risk (Permits):

  • Mitigation: Begin permit applications 16 weeks before facility closure needed
  • Assign dedicated person responsible for agency communication
  • Cost: Management time + permit fees

Contingency Planning

For HIGH risks that mitigation can't eliminate, allocate contingency:

  • Schedule contingency: 10-15% of planned duration for food manufacturing projects
  • Budget contingency: 15-25% depending on risk categories

A 16-week planned project with HIGH risks should allocate:

  • 2-2.5 weeks schedule contingency (3-4 weeks total cushion)
  • 15-25% budget contingency ($100K-$200K on $600-800K project)

The Outcome

Projects with strong risk management:

  • Deliver on schedule 80%+ of the time
  • Experience 10-15% cost overruns vs. budgets with contingency
  • Achieve expected performance targets during commissioning

Projects without risk management:

  • Deliver on schedule 40-50% of the time
  • Experience 20-30% cost overruns
  • Struggle during commissioning due to inadequate planning

For food manufacturing companies, systematic risk identification during FEL and mitigation strategy development prevents surprises that compress schedules and inflate costs.