
A beverage facility plans a 4-month equipment upgrade. The project schedule includes: equipment delivery (6 weeks), installation (4 weeks), commissioning (4 weeks).
What the schedule doesn't account for:
- Equipment supplier delays (historical 2-3 weeks common in food equipment)
- Electrical infrastructure upgrades (discovered during installation, adding 3-4 weeks)
- Integration challenges with existing SCADA (adding 2 weeks to controls work)
- Regulatory approval delays (6-8 weeks for facility modification permits)
The planned 4-month project becomes 7-8 months. The facility loses revenue for 3-4 extra months.
This is a risk management failure—risks existed but weren't identified or mitigated.
The Risk Identification Process
During FEL (feasibility studies), identify risks by category:
Schedule Risks:
- Long-lead equipment (over 8 weeks delivery): HIGH
- Utility infrastructure upgrades: HIGH
- Regulatory approvals: MEDIUM
- Facility modifications (construction): MEDIUM
- Controls integration: MEDIUM
Cost Risks:
- Site condition discoveries: HIGH
- Equipment price escalation: MEDIUM
- Labor cost inflation: MEDIUM
- Vendor change order requests: MEDIUM
Technical Risks:
- New technology with limited food manufacturing experience: HIGH
- Equipment integration with old systems: MEDIUM
- Process parameter uncertainty: MEDIUM
Regulatory Risks:
- FDA or USDA approval required: HIGH
- Environmental discharge permit: MEDIUM
- Local building permits: MEDIUM
Risk Mitigation Strategies
For each identified risk, develop mitigation:
Schedule Risk (Equipment Lead Time):
- Mitigation: Order equipment 8 weeks before needed installation date
- Fallback: Identify backup supplier willing to expedite
- Cost: Minimal (planning)
Schedule Risk (Electrical Upgrade):
- Mitigation: Commission electrical assessment during FEL ($5K-10K)
- Plan upgrade timeline before project execution
- Cost: $5K-10K investigation + identified upgrade cost
Technical Risk (Controls Integration):
- Mitigation: Engage controls integrator early in FEL
- Run integration tests during commissioning phase
- Cost: Early engineering ($10K) + commissioning time
Regulatory Risk (Permits):
- Mitigation: Begin permit applications 16 weeks before facility closure needed
- Assign dedicated person responsible for agency communication
- Cost: Management time + permit fees
Contingency Planning
For HIGH risks that mitigation can't eliminate, allocate contingency:
- Schedule contingency: 10-15% of planned duration for food manufacturing projects
- Budget contingency: 15-25% depending on risk categories
A 16-week planned project with HIGH risks should allocate:
- 2-2.5 weeks schedule contingency (3-4 weeks total cushion)
- 15-25% budget contingency ($100K-$200K on $600-800K project)
The Outcome
Projects with strong risk management:
- Deliver on schedule 80%+ of the time
- Experience 10-15% cost overruns vs. budgets with contingency
- Achieve expected performance targets during commissioning
Projects without risk management:
- Deliver on schedule 40-50% of the time
- Experience 20-30% cost overruns
- Struggle during commissioning due to inadequate planning
For food manufacturing companies, systematic risk identification during FEL and mitigation strategy development prevents surprises that compress schedules and inflate costs.



